We rehabilitated water supply and sewerage at two separate sites. On Teatterikuja in central Helsinki, water supply and sewer lines were renewed in a very narrow street area lined with historic buildings.
In the Kellosilta area in Pasila, existing water supply and sewer lines were renewed.
Two sites, two districts and one contract — but completely different operating environments.
Historic buildings at the edge of the excavation
Teatterikuja is lined with old buildings whose foundations cannot tolerate movement. Excavation next to them required precautions and continuous monitoring.
An alley with no room
Teatterikuja is narrow. The excavator, excavated soil, pipe materials and pedestrians could not all fit in the same space at the same time, so the work sequence was everything.
Two sites, one work team
Teatterikuja and Kellosilta are on different sides of the city. The same work team and equipment served both, so the phasing of the two sites had to be coordinated.
The excavations on Teatterikuja were supported, and settlement gauges were installed on the adjacent buildings. The readings were taken daily during excavation. Excavated soil was removed as soon as it was generated, as there was no room for stockpiling in the alley.
The work sequence was planned so that there was only one machine and one work phase in the alley at a time. Pipe materials were delivered in daily batches, not all at once.
The sites were phased in an interleaved way: when Teatterikuja was waiting for an inspection or materials, the work team moved to Pasila. This kept equipment downtime short.
In the more spacious surroundings of Kellosilta, the work progressed as normal excavation and installation work.