Construction of the Joenranta residential area

Construction of the Joenranta residential area
Location
Kellokoski, Tuusula
Client
Municipality of Tuusula
Schedule
12/2024–12/2025
Contract type
Lump-sum contract, design changes as a turnkey (KVR) contract
Contract value
€3.4M
Services
Urban construction

In Kellokoski, around two kilometres from the centre, we built the streets, pedestrian and cycle paths and park paths of the new Joenranta residential area, as well as the area's municipal engineering.

The scope included water supply, sewer and stormwater lines, a wastewater pumping station, stormwater retention basins, cabling and spare cable conduits. Green areas with a playground and an outdoor gym were also built in the area, as well as boat storage and launching areas. The contract also included a water supply crossing under the river by directional drilling and the construction of water supply and sewer lines on the west side of the river.

Joenranta was also a pilot construction project that sought cost-effective ways to reduce the carbon footprint of municipal engineering construction.

01

Lower carbon at no extra cost

The project had to demonstrate that municipal engineering can be built with lower carbon emissions without compromising cost-efficiency. A CO₂ emissions calculation was carried out for the investment, and a limit value was set for the emissions.

02

Every choice through the lens of the carbon footprint

Material choices, transport and work methods were reviewed from the perspective of the carbon footprint. The environment was also taken into account in the choice of machines and fuels.

03

The infrastructure for a whole residential area at once

Water supply and sewerage, stormwater management, streets and green and recreational areas were all delivered in the same contract – and the water supply and sewerage was taken under the river.

Wherever possible, materials available on site were used and material transport was minimised. Work methods and materials were selected so that the carbon footprint could be reduced cost-effectively.

The river crossing was carried out by directional drilling, and the contract included a total of around 750 metres of directional drilling.

The contract included 1.5 kilometres of main water supply and sewer lines, 77 plot connections and five stormwater basins, as well as the area's boat shore, playground and outdoor gym.

As a result, the carbon footprint of the construction was reduced by 29%.

Photos

From the site

Construction of the Joenranta residential area
Construction of the Joenranta residential area
Construction of the Joenranta residential area

Responsibility on site

Good work starts before the first work phase.

We plan the work, identify the risks and ensure quality as the work progresses. Inspections and documentation are part of the job from the start all the way to handover.

Safety — Everyone home safe.

Induction, risk assessment and safety observations are part of everyday life on site.

Quality — Inspected before it's covered.

Plans, inspections of work phases and documentation keep quality traceable.

Environment — Less waste on site.

We carefully plan the use of materials, transport and energy consumption.

Moisture management — Protection is part of the job.

Protecting materials and monitoring moisture are planned as part of construction.

Projects

These are the projects we have helped build.

Gräsantori street and bridge contract
Foundation engineering
Gräsantori street and bridge contract

A street, a square and two new bridges on soft clay, in the middle of traffic.

Olari, Espoo · 3/2026–7/2027 Explore the project
Pohjois-Haaga station renovation
Renovation
Pohjois-Haaga station renovation

Major renovation of a station platform and station building during a ten-week traffic shutdown, around the clock.

Pohjois-Haaga, Helsinki · 2026–2027 Explore the project
Lahela campus and Lahelanorsi
Foundation engineering
Lahela campus and Lahelanorsi

Streets, a bridge and municipal engineering for a new detailed plan area on soft, flood-prone ground.

Lahela, Tuusula · 3/2026– Explore the project
Gräsantulli – wastewater bypass pumping
Urban construction
Gräsantulli – wastewater bypass pumping

1,500 l/s bypass pumping and connections to a 1,800 mm sewer in operation, in three days.

Olari, Espoo · 2/2024–12/2024 Explore the project
Construction of the Joenranta residential area
Urban construction
Construction of the Joenranta residential area

Streets and municipal engineering for a new residential area with a lower carbon footprint – the carbon footprint was reduced by 29%.

Kellokoski, Tuusula · 12/2024–12/2025 Explore the project
Sinimäentie–Kalevalantie rehabilitation
Foundation engineering
Sinimäentie–Kalevalantie rehabilitation

Around 4.1 kilometres of water supply and sewer lines and street improvements on busy streets.

Mankkaa, Espoo · 5/2024–12/2025 Explore the project
Kruunuvuori oil tank restoration
Renovation
Kruunuvuori oil tank restoration

Restoration of an old oil tank and steel stairs to the top of a rock with no road access.

Kruunuvuorenranta, Helsinki · 2025 Explore the project
Maria campus – Lastenkodinkatu bridge
Urban construction
Maria campus – Lastenkodinkatu bridge

A post-tensioned concrete bridge and a natural stone wall in the middle of Baana traffic.

Kamppi, Helsinki · 11/2024–12/2025 Explore the project
Nurmilinnunpuisto park
Foundation engineering
Nurmilinnunpuisto park

Park paths, play areas and sports courts on challenging ground conditions.

Karakallio, Espoo · 9/2024–1/2025 Explore the project
Mannerheimintie between Postikatu and Reijolankatu
Urban construction
Mannerheimintie between Postikatu and Reijolankatu

Rehabilitation of the structures, utilities and tram tracks of Helsinki's main street in the middle of heavy traffic.

Mannerheimintie, Helsinki · 2023–2025 Explore the project