Gräsantulli – wastewater bypass pumping

Gräsantulli – wastewater bypass pumping
Location
Olari, Espoo
Client
City of Espoo, City Infrastructure Centre
Schedule
2/2024–12/2024
Contract type
General contract
Contract value
€1.8M
Services
Urban construction

In the Gräsantulli street and water supply contract, we renewed municipal engineering in a built-up urban environment. The contract included renewing large main wastewater lines, a water main and stormwater sewers, as well as building the street area.

A key work phase was connecting the new wastewater line to the network in operation and removing the old line over a distance of around 200 metres. Wastewater flow had to be secured throughout the connection works, and the design of the bypass pumping was the contractor's responsibility.

The bypass pumping was carried out over three days. The pumping rate was 1,500 l/s, and around 25 people were working in the small work area during the connection works.

01

A large bypass pumping volume

1,500 l/s means one and a half cubic metres of wastewater per second. The pumping arrangements, temporary connections and commissioning of the new network had to form one functioning whole.

02

Connections to the network in operation

New manholes were installed in a 1,800 mm concrete sewer line in operation. The manhole installations and the bypass pumping had to be coordinated so that the wastewater could be diverted past the work phase into a tunnel shaft.

03

A built-up street area with traffic

The work area contained a large number of existing pipes and cables as well as an old 400 mm cast-iron water main. The bypass pumping also had to take into account street traffic and access to properties.

The bypass pumping was planned to be completed within three days – and it was. During this time, the new manholes were installed in the 1,800 mm concrete sewer line.

The wastewater was diverted past the work phase with 1,500 l/s pumping, discharging into a tunnel shaft.

The connection works were completed in less than a week.

Kuvat

Työmaalta

Gräsantulli – wastewater bypass pumping
Gräsantulli – wastewater bypass pumping
Gräsantulli – wastewater bypass pumping

Responsibility on site

Good work starts before the first work phase.

We plan the work, identify the risks and ensure quality as the work progresses. Inspections and documentation are part of the job from the start all the way to handover.

Safety — Everyone home safe.

Induction, risk assessment and safety observations are part of everyday life on site.

Quality — Inspected before it's covered.

Plans, inspections of work phases and documentation keep quality traceable.

Environment — Less waste on site.

We carefully plan the use of materials, transport and energy consumption.

Moisture management — Protection is part of the job.

Protecting materials and monitoring moisture are planned as part of construction.

Projects

These are the projects we have helped build.

Gräsantori street and bridge contract
Foundation engineering
Gräsantori street and bridge contract

A street, a square and two new bridges on soft clay, in the middle of traffic.

Olari, Espoo · 3/2026–7/2027 Explore the project
Pohjois-Haaga station renovation
Renovation
Pohjois-Haaga station renovation

Major renovation of a station platform and station building during a ten-week traffic shutdown, around the clock.

Pohjois-Haaga, Helsinki · 2026–2027 Explore the project
Lahela campus and Lahelanorsi
Foundation engineering
Lahela campus and Lahelanorsi

Streets, a bridge and municipal engineering for a new detailed plan area on soft, flood-prone ground.

Lahela, Tuusula · 3/2026– Explore the project
Gräsantulli – wastewater bypass pumping
Urban construction
Gräsantulli – wastewater bypass pumping

1,500 l/s bypass pumping and connections to a 1,800 mm sewer in operation, in three days.

Olari, Espoo · 2/2024–12/2024 Explore the project
Construction of the Joenranta residential area
Urban construction
Construction of the Joenranta residential area

Streets and municipal engineering for a new residential area with a lower carbon footprint – the carbon footprint was reduced by 29%.

Kellokoski, Tuusula · 12/2024–12/2025 Explore the project
Sinimäentie–Kalevalantie rehabilitation
Foundation engineering
Sinimäentie–Kalevalantie rehabilitation

Around 4.1 kilometres of water supply and sewer lines and street improvements on busy streets.

Mankkaa, Espoo · 5/2024–12/2025 Explore the project
Kruunuvuori oil tank restoration
Renovation
Kruunuvuori oil tank restoration

Restoration of an old oil tank and steel stairs to the top of a rock with no road access.

Kruunuvuorenranta, Helsinki · 2025 Explore the project
Maria campus – Lastenkodinkatu bridge
Urban construction
Maria campus – Lastenkodinkatu bridge

A post-tensioned concrete bridge and a natural stone wall in the middle of Baana traffic.

Kamppi, Helsinki · 11/2024–12/2025 Explore the project
Nurmilinnunpuisto park
Foundation engineering
Nurmilinnunpuisto park

Park paths, play areas and sports courts on challenging ground conditions.

Karakallio, Espoo · 9/2024–1/2025 Explore the project
Mannerheimintie between Postikatu and Reijolankatu
Urban construction
Mannerheimintie between Postikatu and Reijolankatu

Rehabilitation of the structures, utilities and tram tracks of Helsinki's main street in the middle of heavy traffic.

Mannerheimintie, Helsinki · 2023–2025 Explore the project