In Olari, Espoo, we are rebuilding a street area of around 400 metres with its municipal engineering, as well as a new square, a dog park and a rug washing area. The grade of the area is being raised by around one metre.
The water supply and sewer lines are being renewed, including wastewater, stormwater and water mains. We are also installing district heating and telecom cable conduits and renewing the area's lighting.
Two old bridges were demolished, and new ones are being built in their place.
Weak subsoil
The soil in the area is soft clay. The square, the street and the bridge abutments required several different ground improvement methods.
Bridges in a sensitive environment
Both bridges cross the Gräsanoja brook, a sensitive trout stream and part of a movement corridor for flying squirrels. Olarsbynsilta bridge is also located within the ancient monument area of the medieval village of Gräsa, where excavation was carried out under the supervision of an archaeologist.
A street in traffic and network relocations
The work is carried out while traffic continues on a collector street in the buffer zone of the West Metro. District heating, water supply and cable relocations were coordinated with several network owners.
The ground was improved with column stabilisation, with panel stabilisation at the bridge abutments, foam glass lightweight fill, steel pipe and reinforced concrete piles and pile slabs. During the contract, foam glass replaced part of the column stabilisation.
Olarinluomansilta bridge is a cast-in-place reinforced concrete slab frame bridge on driven piles, and it replaced an old culvert bridge in a sea flood zone. Olarsbynsilta bridge is a steel truss bridge with a timber deck, built on a drilled pile combi wall and rock anchors. The needs of the brook and the flying squirrels were taken into account in the work methods and schedule.
The work was phased and the traffic arrangements were planned in detail. The machines used renewable fuels, the emission values of natural aggregates were taken into account, and the work was managed using the Infrakit project bank, information models and machine control.
Cast-in-place concrete totals 1,500 m³ in the pile slab of the square, 300 m³ in Olarinluomansilta bridge and 50 m³ in Olarsbynsilta bridge. Stone work covers almost 4,000 m².