We carried out a major renovation of the ticket hall level of Sörnäinen metro station. At street level, entrances A and B were partly demolished and renewed, the pressure relief shaft was clad, and the waterproofing of the ticket hall roof deck and its associated structures was renewed in the Vaasanpuistikko square. Two lifts were also renewed.
The station had highly demanding building services systems and renovations of them. The layout of the technical rooms was also changed at the technical level.
The station remained in passenger use throughout construction.
The station stayed open for two years
Passenger traffic flowed through the station throughout the contract. The site and the passengers shared the same spaces for two years, and the routes had to work every day, including at rush hour.
Waterproofing under a square
The waterproofing of the ticket hall roof deck was renewed in the Vaasanpuistikko square — in other words, the station's roof is also a city square. The work progressed from the top down while passengers passed underneath.
Building services that can't be switched off
The station's building services systems were renovated while in use. Ventilation, power supply and safety systems had to work without interruption, even though they were being renewed in parts.
Throughout the contract, a clear, fenced route through the station was provided for passengers and moved according to the work phases. Route changes were made at night so that the first passenger in the morning found the arrangements ready.
Entrances A and B were renewed one after the other, not at the same time. One of the station's entrances was always in use.
The deck waterproofing was renewed section by section. Each section was opened, waterproofed and closed under weather protection to prevent water from getting into the spaces below the station.
The building services systems were renovated in subsystems so that the old system remained in service until the new one had been test-run. Shutdowns of the safety systems were scheduled outside traffic hours and agreed separately with the client.