In Ruskeasuo, we rehabilitated the street areas of Mannerheimintie, Nauvontie and Korppaanmäentie. The work included water supply and sewerage, the structural layers of the streets, technical systems and tram tracks.
A pile-founded noise barrier was also built on Nauvontie.
The site was located on one of Helsinki's busiest stretches of street. Trams, buses and cars use Mannerheimintie at the same time, and traffic could not be stopped.
The trams kept running the whole time
The tracks were renewed on a section served by several tram lines. The track replacement work had to fit into the operator's shutdowns, which lasted one weekend at a time.
All utilities in the same excavation
Water supply and sewerage, cables and street lighting ran in the same narrow excavation next to the tramway. Up-to-date information was not available on all the old utility lines.
A noise barrier in soft ground
The Nauvontie noise barrier was founded on piles right next to a carriageway in use. Piling causes vibration, and the vibration had to be kept within limits that the adjacent buildings and street structures could withstand.
The street section was divided into work phases, each with its own traffic arrangements. Traffic lanes were moved in phases so that traffic kept flowing the whole time, even as the lanes changed places.
The tram track replacements were scheduled for pre-agreed weekend shutdowns. The rails, supplies and equipment were on site on Friday, and traffic resumed on Monday morning.
The old utility lines were located with trial pits before the actual excavation. It cost a few days up front and saved weeks later on.
Vibration monitoring and measuring points on the adjacent structures were used during the piling of the noise barrier. The readings were reviewed with the client as the work progressed. There were no deviations.