Location
Hyrylä, Tuusula
Client
Arkta Rakennuskultti Oy (developer: Municipality of Tuusula)
Schedule
12/2020–6/2022
Contract type
Subcontract
Contract value
€1M
Services
Foundation engineering, Urban construction

We carried out the foundation and yard works for the Martta Wendelin day care centre in Hyrylä, Tuusula. Measured by volume, the timber early childhood education building is Finland's largest solid wood day care centre, with room for around 200 children in ten groups.

The developer was the Municipality of Tuusula and the main contractor Arkta Rakennuskultti Oy. The day care centre was taken into use in August 2022.

In 2023, the day care centre won the Finlandia Prize for Architecture.

01

Winter work on a tight schedule

The foundation and yard works were carried out in winter, and the schedule was tight.

Kuvat

Työmaalta

Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre
Martta Wendelin day care centre

Responsibility on site

Good work starts before the first work phase.

We plan the work, identify the risks and ensure quality as the work progresses. Inspections and documentation are part of the job from the start all the way to handover.

Safety — Everyone home safe.

Induction, risk assessment and safety observations are part of everyday life on site.

Quality — Inspected before it's covered.

Plans, inspections of work phases and documentation keep quality traceable.

Environment — Less waste on site.

We carefully plan the use of materials, transport and energy consumption.

Moisture management — Protection is part of the job.

Protecting materials and monitoring moisture are planned as part of construction.

Projects

These are the projects we have helped build.

Gräsantori street and bridge contract
Foundation engineering
Gräsantori street and bridge contract

A street, a square and two new bridges on soft clay, in the middle of traffic.

Olari, Espoo · 3/2026–7/2027 Explore the project
Pohjois-Haaga station renovation
Renovation
Pohjois-Haaga station renovation

Major renovation of a station platform and station building during a ten-week traffic shutdown, around the clock.

Pohjois-Haaga, Helsinki · 2026–2027 Explore the project
Lahela campus and Lahelanorsi
Foundation engineering
Lahela campus and Lahelanorsi

Streets, a bridge and municipal engineering for a new detailed plan area on soft, flood-prone ground.

Lahela, Tuusula · 3/2026– Explore the project
Gräsantulli – wastewater bypass pumping
Urban construction
Gräsantulli – wastewater bypass pumping

1,500 l/s bypass pumping and connections to a 1,800 mm sewer in operation, in three days.

Olari, Espoo · 2/2024–12/2024 Explore the project
Construction of the Joenranta residential area
Urban construction
Construction of the Joenranta residential area

Streets and municipal engineering for a new residential area with a lower carbon footprint – the carbon footprint was reduced by 29%.

Kellokoski, Tuusula · 12/2024–12/2025 Explore the project
Sinimäentie–Kalevalantie rehabilitation
Foundation engineering
Sinimäentie–Kalevalantie rehabilitation

Around 4.1 kilometres of water supply and sewer lines and street improvements on busy streets.

Mankkaa, Espoo · 5/2024–12/2025 Explore the project
Kruunuvuori oil tank restoration
Renovation
Kruunuvuori oil tank restoration

Restoration of an old oil tank and steel stairs to the top of a rock with no road access.

Kruunuvuorenranta, Helsinki · 2025 Explore the project
Maria campus – Lastenkodinkatu bridge
Urban construction
Maria campus – Lastenkodinkatu bridge

A post-tensioned concrete bridge and a natural stone wall in the middle of Baana traffic.

Kamppi, Helsinki · 11/2024–12/2025 Explore the project
Nurmilinnunpuisto park
Foundation engineering
Nurmilinnunpuisto park

Park paths, play areas and sports courts on challenging ground conditions.

Karakallio, Espoo · 9/2024–1/2025 Explore the project
Mannerheimintie between Postikatu and Reijolankatu
Urban construction
Mannerheimintie between Postikatu and Reijolankatu

Rehabilitation of the structures, utilities and tram tracks of Helsinki's main street in the middle of heavy traffic.

Mannerheimintie, Helsinki · 2023–2025 Explore the project