We built new structures to improve fire safety at Rautatientori metro station. A smoke barrier structure consisting of a cast-in-place concrete beam and steel structures was built at platform level, and all building services at platform level were renewed.
New smoke doors were installed in the metro tunnels. Additional space was excavated in the rock tunnels for the doors, and the jamb structures were cast in concrete.
Rautatientori is Finland's busiest metro station. The main works were carried out during a traffic shutdown in summer 2024, and outside the shutdown the station remained in passenger use.
The goal was simple: after the work, the metro had to run — more safely.
The traffic shutdown doesn't bend
Rock excavation, concreting and door installation had to fit within the summer traffic shutdown. The shutdown dates had been fixed a year earlier and could not be negotiated. Everything scheduled for the shutdown had to be planned, and the materials had to be on site, before the first working day.
An underground site in the heart of the city
Materials, equipment and workers reached the station via the same routes as passengers. Concrete, steel structures and excavated rock were moved through restricted openings at night, beneath Helsinki's busiest stretch of street.
Four trades in the same space
Rock excavation, concrete structures, steel installation and building services all took place in the same spaces. One delayed work phase would have stopped the other three, because there was no room to make way.
The work phases scheduled for the shutdown were fully planned during the previous winter. Blasting patterns, reinforcement and formwork were dimensioned in advance, and materials were stored at the station before the shutdown began.
Production was managed daily. Each work phase was given its own time window and its own space, and the start of the next phase was tied to the completion of the previous one — not to a calendar date.
Excavated rock and demolition waste were removed at night, when the city centre's street network was clear. The same route served material deliveries in the opposite direction.
The concrete beam of the smoke barrier structure was cast in place, and the steel structures were installed on top of it immediately after the formwork was removed. The smoke doors were installed in the rock tunnels once the rock excavation and jamb structures were completed.
Metro traffic resumed on schedule after the shutdown.