We rehabilitated the streets of the Telakkaranta area, including their structural layers, utilities and tram tracks.
A new connection was drilled into the wastewater tunnel, and the overflow to the sea was built by divers. Part of the municipal engineering was installed underwater.
The area is a dense urban environment on the Helsinki waterfront, and the site was bordered on all sides by other ongoing construction sites.
Working underwater
The overflow to the sea and part of the municipal engineering were installed by divers. Underwater work progresses more slowly, depends on the weather and leaves no room for improvisation — every work phase is fully planned on the surface.
Other sites as neighbours
The site bordered on several other construction sites. Access roads, lifting areas and the timing of work phases had to be coordinated with the neighbours on a daily basis, not at contract level.
Drilling into a wastewater tunnel in operation
The new connection was drilled into a wastewater tunnel in operation. The work had to be done without interrupting sewerage and without endangering the tunnel structures.
The underwater work phases were fully planned on the surface and reviewed before diving. The structures were prefabricated on land as far as possible, which kept the underwater part short and manageable.
The drilling of the tunnel connection was scheduled for a period of low flow, and the tunnel structures were monitored during the work. Sewerage remained in use the whole time.
A joint weekly meeting was held with the neighbouring sites to agree on the following week's lifts, access roads and use of space. This eliminated most overlaps before they reached the site.
Despite the exceptional nature of the project, the contract was completed ahead of schedule.