We converted the roads of the Juhlakallio area in Kirkkonummi into streets and renewed the area's municipal engineering. A total of 20 roads were converted into streets, and water mains, sewers and stormwater sewers were built as part of the street construction.
The contract included sections of Vanha Rantatie, Vanha Heikkiläntie, Tohtorinpolku, Vanha Sairaalatie and Viulunrakentajantie, the junction of Heikkiläntie and Vanha Rantatie, as well as pedestrian and cycle paths and parks. Street construction totalled around 4,000 metres.
A deep excavation next to the railway
The water supply and sewer excavation was carried out close to the railway area over a distance of around 800 metres. At its deepest, the open excavation was around five metres deep.
An extensive street network in a single contract
The contract covered 20 roads. Street construction was combined with the construction of water supply and sewerage, stormwater systems, lighting and parks.
Rock was excavated in the water supply and sewer trench, and the excavation was supported with trench shoring elements.
In the street areas, we built retaining walls from retaining wall elements, gabion walls, lighting, paving, planting and asphalt surfaces. We also built Tohtorinaukio square with its pergolas and a playground.
The target completion date for the contract was 30 November 2024, but the project was completed as early as August 2024, more than three months ahead of schedule.