In Karakallio, Espoo, we built Nurmilinnunpuisto, Nurmilampi, Nurminiitty and Rastaskukkula.
The contract included restoring old park paths and building new, lit paths. We also built two play areas, an outdoor gym, a basketball court and an asphalt games area, as well as the surrounding green areas.
The park lighting was completely renewed, and DN800 steel culverts were installed in the area.
Challenging ground conditions
The ground conditions on the site were challenging, and the areas to be asphalted required ground improvement.
The ground conditions of the asphalted areas were improved with column stabilisation. A total of around 5,000 metres of columns with a diameter of 600 mm were installed.