Pirkkolan Plotti

Pirkkolan Plotti
Location
Pirkkola, Helsinki
Client
City of Helsinki
Schedule
6/2022
Contract type
General contract
Contract value
676 000 €
Services
Urban construction

We renovated Plotti in Pirkkola sports park, a popular outdoor swimming area among Helsinki residents.

The contract included new retaining walls, new pressure lines and a membrane structure with bentonite mats installed at the bottom of the pool.

01

An outdoor pool with indoor pool requirements

The aim was for the pool to match an indoor swimming pool. There are hardly any similar outdoor facilities in Finland, so no ready-made solutions were available.

02

The filter system was not sufficient

The original plans did not include upgrading the filter system, and it was soon found to be insufficient.

03

Fixing the membrane structure

The fixing of the membrane structure to the concrete wall also proved insufficient in the original plans.

We identified the shortcomings in the plans during the work and actively brought them to the designers to resolve.

The problems were investigated several times together with the client. After the first summer of use, we fixed the issues that had come up in use.

As a result, the pool was made to work, even though the criteria for an indoor pool cannot be fully met outdoors.

Photos

From the site

Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti
Pirkkolan Plotti

Responsibility on site

Good work starts before the first work phase.

We plan the work, identify the risks and ensure quality as the work progresses. Inspections and documentation are part of the job from the start all the way to handover.

Safety — Everyone home safe.

Induction, risk assessment and safety observations are part of everyday life on site.

Quality — Inspected before it's covered.

Plans, inspections of work phases and documentation keep quality traceable.

Environment — Less waste on site.

We carefully plan the use of materials, transport and energy consumption.

Moisture management — Protection is part of the job.

Protecting materials and monitoring moisture are planned as part of construction.

Projects

These are the projects we have helped build.

Gräsantori street and bridge contract
Foundation engineering
Gräsantori street and bridge contract

A street, a square and two new bridges on soft clay, in the middle of traffic.

Olari, Espoo · 3/2026–7/2027 Explore the project
Pohjois-Haaga station renovation
Renovation
Pohjois-Haaga station renovation

Major renovation of a station platform and station building during a ten-week traffic shutdown, around the clock.

Pohjois-Haaga, Helsinki · 2026–2027 Explore the project
Lahela campus and Lahelanorsi
Foundation engineering
Lahela campus and Lahelanorsi

Streets, a bridge and municipal engineering for a new detailed plan area on soft, flood-prone ground.

Lahela, Tuusula · 3/2026– Explore the project
Gräsantulli – wastewater bypass pumping
Urban construction
Gräsantulli – wastewater bypass pumping

1,500 l/s bypass pumping and connections to a 1,800 mm sewer in operation, in three days.

Olari, Espoo · 2/2024–12/2024 Explore the project
Construction of the Joenranta residential area
Urban construction
Construction of the Joenranta residential area

Streets and municipal engineering for a new residential area with a lower carbon footprint – the carbon footprint was reduced by 29%.

Kellokoski, Tuusula · 12/2024–12/2025 Explore the project
Sinimäentie–Kalevalantie rehabilitation
Foundation engineering
Sinimäentie–Kalevalantie rehabilitation

Around 4.1 kilometres of water supply and sewer lines and street improvements on busy streets.

Mankkaa, Espoo · 5/2024–12/2025 Explore the project
Kruunuvuori oil tank restoration
Renovation
Kruunuvuori oil tank restoration

Restoration of an old oil tank and steel stairs to the top of a rock with no road access.

Kruunuvuorenranta, Helsinki · 2025 Explore the project
Maria campus – Lastenkodinkatu bridge
Urban construction
Maria campus – Lastenkodinkatu bridge

A post-tensioned concrete bridge and a natural stone wall in the middle of Baana traffic.

Kamppi, Helsinki · 11/2024–12/2025 Explore the project
Nurmilinnunpuisto park
Foundation engineering
Nurmilinnunpuisto park

Park paths, play areas and sports courts on challenging ground conditions.

Karakallio, Espoo · 9/2024–1/2025 Explore the project
Mannerheimintie between Postikatu and Reijolankatu
Urban construction
Mannerheimintie between Postikatu and Reijolankatu

Rehabilitation of the structures, utilities and tram tracks of Helsinki's main street in the middle of heavy traffic.

Mannerheimintie, Helsinki · 2023–2025 Explore the project