We carried out a major renovation of the Pohjois-Haaga station platform and station building. During a ten-week traffic shutdown, the surface structures of the platform levels were demolished and new ones were built to current regulations under weather protection.
The platform canopy was renovated, and the roof structures of the station hall were demolished and renewed during the shutdown. Almost all building services were renewed, as were the steel and glass structures, doors and surface structures.
By the end of 2026, the station hall, the commercial space and the staff facilities will open fully renovated.
Ten weeks, around the clock
The schedule was extremely tight, and work was carried out 24/7 for ten weeks. Certain work phases and areas had to be completed during the shutdown so that the electrified railway could be put back into use and safe, accessible routes could be opened for passengers.
Another contract in the middle of our site
The Finnish Transport Infrastructure Agency's railway bridge renovation contract was in the middle of our site. Logistics were coordinated with them.
Surprises revealed by demolition
Demolishing the old structure revealed things that could not be foreseen in the plans – and the schedule left no room for waiting.
The work phases were planned as far in advance as possible, and both resources and materials were reserved in advance, because there was no room for disruptions.
Solutions to the surprises revealed by the demolition were found together with the designers and the client.
The work areas were divided into sections so that each section could be assigned its own work team. This kept the 240-metre platform section on schedule.