In the Gräsantulli street and water supply contract, we renewed municipal engineering in a built-up urban environment. The contract included renewing large main wastewater lines, a water main and stormwater sewers, as well as building the street area.
A key work phase was connecting the new wastewater line to the network in operation and removing the old line over a distance of around 200 metres. Wastewater flow had to be secured throughout the connection works, and the design of the bypass pumping was the contractor's responsibility.
The bypass pumping was carried out over three days. The pumping rate was 1,500 l/s, and around 25 people were working in the small work area during the connection works.
A large bypass pumping volume
1,500 l/s means one and a half cubic metres of wastewater per second. The pumping arrangements, temporary connections and commissioning of the new network had to form one functioning whole.
Connections to the network in operation
New manholes were installed in a 1,800 mm concrete sewer line in operation. The manhole installations and the bypass pumping had to be coordinated so that the wastewater could be diverted past the work phase into a tunnel shaft.
A built-up street area with traffic
The work area contained a large number of existing pipes and cables as well as an old 400 mm cast-iron water main. The bypass pumping also had to take into account street traffic and access to properties.
The bypass pumping was planned to be completed within three days – and it was. During this time, the new manholes were installed in the 1,800 mm concrete sewer line.
The wastewater was diverted past the work phase with 1,500 l/s pumping, discharging into a tunnel shaft.
The connection works were completed in less than a week.