Sinimäentie–Kalevalantie rehabilitation

Sinimäentie–Kalevalantie rehabilitation
Location
Mankkaa, Espoo
Client
HSY
Schedule
5/2024–12/2025
Contract type
General contract
Contract value
€12.7M
Services
Foundation engineering, Urban construction

We built and rehabilitated HSY's water supply and sewer network and improved streets in Mankkaa, Espoo, on sections of Mankkaantie, Vanha Mankkaantie, Koivuviidantie and Kalevalantie.

A total of around 4,100 metres of water supply and sewer lines were built, mainly by excavation and partly by trenchless methods. Around 3,000 metres of DN 600 and around 1,000 metres of DN 400 trunk water mains were built, around 1,310 metres of 2 × DN 600 pressure sewers and a total of around 2,100 metres of DN 200–800 wastewater sewers. The contract also included a control valve station, three district metering chambers, as well as equipment chambers, flushing posts and fire water stations.

The lighting, operator conduits and all surface structures of the streets were renewed: paving, asphalt, green areas and traffic control devices and signs.

01

Large pipes in the middle of heavy traffic

The contract was carried out on very busy streets. The DN 600 trunk lines and twin pressure sewers required wide excavations in the same street area where traffic flowed the whole time.

02

Soft ground and hard rock in the same contract

Part of the line ran through soil requiring ground improvement, part through rock. The same contract required both pile slabs and column stabilisation and rock excavation in the street area.

03

Renewing old lines while in use

Some of the water mains and sewers were renewed by sliplining and relining the old pipes. The work had to be coordinated with the network in operation.

The excavations were supported with sheet pile walls, and the contract included around 4,000 m² of sheet piling.

Ground improvement was carried out with pile slabs and column stabilisation. The rock in the street area was excavated both by blasting and by wedging.

Using trenchless methods, around 240 metres of distribution water main were renewed by sliplining the old pipes, and around 300 metres of wastewater and stormwater sewers by relining.

Finally, the streets were completed with new lighting, paving, asphalt and green areas.

Photos

From the site

Sinimäentie–Kalevalantie rehabilitation
Sinimäentie–Kalevalantie rehabilitation
Sinimäentie–Kalevalantie rehabilitation
Sinimäentie–Kalevalantie rehabilitation
Sinimäentie–Kalevalantie rehabilitation
Sinimäentie–Kalevalantie rehabilitation
Sinimäentie–Kalevalantie rehabilitation
Sinimäentie–Kalevalantie rehabilitation

Responsibility on site

Good work starts before the first work phase.

We plan the work, identify the risks and ensure quality as the work progresses. Inspections and documentation are part of the job from the start all the way to handover.

Safety — Everyone home safe.

Induction, risk assessment and safety observations are part of everyday life on site.

Quality — Inspected before it's covered.

Plans, inspections of work phases and documentation keep quality traceable.

Environment — Less waste on site.

We carefully plan the use of materials, transport and energy consumption.

Moisture management — Protection is part of the job.

Protecting materials and monitoring moisture are planned as part of construction.

Projects

These are the projects we have helped build.

Gräsantori street and bridge contract
Foundation engineering
Gräsantori street and bridge contract

A street, a square and two new bridges on soft clay, in the middle of traffic.

Olari, Espoo · 3/2026–7/2027 Explore the project
Pohjois-Haaga station renovation
Renovation
Pohjois-Haaga station renovation

Major renovation of a station platform and station building during a ten-week traffic shutdown, around the clock.

Pohjois-Haaga, Helsinki · 2026–2027 Explore the project
Lahela campus and Lahelanorsi
Foundation engineering
Lahela campus and Lahelanorsi

Streets, a bridge and municipal engineering for a new detailed plan area on soft, flood-prone ground.

Lahela, Tuusula · 3/2026– Explore the project
Gräsantulli – wastewater bypass pumping
Urban construction
Gräsantulli – wastewater bypass pumping

1,500 l/s bypass pumping and connections to a 1,800 mm sewer in operation, in three days.

Olari, Espoo · 2/2024–12/2024 Explore the project
Construction of the Joenranta residential area
Urban construction
Construction of the Joenranta residential area

Streets and municipal engineering for a new residential area with a lower carbon footprint – the carbon footprint was reduced by 29%.

Kellokoski, Tuusula · 12/2024–12/2025 Explore the project
Sinimäentie–Kalevalantie rehabilitation
Foundation engineering
Sinimäentie–Kalevalantie rehabilitation

Around 4.1 kilometres of water supply and sewer lines and street improvements on busy streets.

Mankkaa, Espoo · 5/2024–12/2025 Explore the project
Kruunuvuori oil tank restoration
Renovation
Kruunuvuori oil tank restoration

Restoration of an old oil tank and steel stairs to the top of a rock with no road access.

Kruunuvuorenranta, Helsinki · 2025 Explore the project
Maria campus – Lastenkodinkatu bridge
Urban construction
Maria campus – Lastenkodinkatu bridge

A post-tensioned concrete bridge and a natural stone wall in the middle of Baana traffic.

Kamppi, Helsinki · 11/2024–12/2025 Explore the project
Nurmilinnunpuisto park
Foundation engineering
Nurmilinnunpuisto park

Park paths, play areas and sports courts on challenging ground conditions.

Karakallio, Espoo · 9/2024–1/2025 Explore the project
Mannerheimintie between Postikatu and Reijolankatu
Urban construction
Mannerheimintie between Postikatu and Reijolankatu

Rehabilitation of the structures, utilities and tram tracks of Helsinki's main street in the middle of heavy traffic.

Mannerheimintie, Helsinki · 2023–2025 Explore the project