We built a new steel pedestrian overpass on Länsisatamankatu, as well as cast-in-place retaining walls clad with precast concrete elements. The contract also included installing granite paving on Länsisatamankatu.
The bridge was prefabricated elsewhere and transported to the site by sea. The transport route was simulated, and a shutdown of public transport was planned for the move.
The bridge arrived by sea
The prefabricated steel bridge was transported to the site by sea and moved from the harbour into place by land. Every bend, gradient and overhead line along the route had to be measured in advance — a move like this cannot be stopped halfway.
One lift, one chance
The bridge was installed during a traffic shutdown, with a single time window reserved for the lift. If the lift had failed, the next opportunity would have been weeks away.
Retaining walls before the bridge
The cast-in-place retaining walls had to be completed and clad before the bridge was installed. The strength development of the concrete tied up the early part of the schedule, and there was no room for compromise.
The transport route was simulated before the move. The dimensions, turning radii and clearances along the route were checked on site, and the public transport shutdown was agreed with the transport operator months in advance.
The retaining wall pours were scheduled so that the concrete had time to reach the required strength before the lifting day. The element cladding was installed once the pours had cured.
The lifting day was rehearsed step by step in advance: equipment, lifting accessories, work team and contingency plan. The lift was carried out during the shutdown, and traffic resumed within the same shutdown.
The granite paving was installed after the bridge was completed, once the heavy equipment had left the street area.