We rebuilt Erottaja square and improved the adjoining streets. The square covers around 4,000 square metres in central Helsinki.
Around one hundred metres of water mains and two hundred metres of sewers were renewed in the square, and new cable conduits and a base course were built. The surface was paved with 4,000 square metres of granite slabs in Finnish stone types — three sizes and six colours in the same laying pattern.
We planted trees in a load-bearing growing medium and replaced the growing medium of three old lime trees using the vacuum excavation method. Four metal and granite works of art with plinths were installed in the square, as well as round benches with cast foundations around the old trees, fixed benches, bicycle racks and information boards.
On the adjoining streets — Erottajankatu, Bulevardi, Mannerheimintie and Eteläesplanadi — paving, traffic light, cable conduit and asphalting works were carried out.
The city centre doesn't close
The site was located in Helsinki's busiest pedestrian area, with tram and bus traffic passing through it. A significant part of the work was done at night, because during the day there was simply no room in the area.
The laying pattern leaves no room for error
Four thousand square metres of granite in three sizes and six colours is in practice one large pattern. A stone laid in the wrong place shows in the finished surface and cannot be fixed by moving a single slab.
The old lime trees had to be saved
The growing medium of three old lime trees was replaced with a load-bearing one using the vacuum excavation method. The roots could not be damaged, and the work was done on the trees' terms, according to their growing season.
The square was divided into sections, with one section under construction at a time. At every stage, pedestrians had a marked route through the square, and tram and bus traffic could pass.
Noisy and space-intensive work phases were carried out at night. Stone deliveries, lifts and asphalting were scheduled for times when the city centre was quiet.
The granite paving was laid stone by stone according to the plan, and each section was inspected before the next one was started. The stone batches were sorted by colour as soon as they were received.
The growing medium of the lime trees was replaced with a vacuum excavator without damaging the roots, and the work was timed for the right season for the trees. The round benches were cast around the trees only after the growing medium was completed.
The works of art were installed on their granite plinths last, once the surrounding surface was finished.