The Kuusijärvi smoke saunas won the 2026 Finlandia Prize for Architecture. We were the main contractor for the City of Vantaa's project. The buildings were designed by Mer Arkkitehdit and Arkkitehtuuri- ja muotoilutoimisto Talli, and for us as builders, the most important thing was to bring their vision to life as carefully as possible.
We built four new service buildings in the Kuusijärvi outdoor recreation area: two smoke saunas of laminated log construction, a changing room building of block construction and an information and toilet building.
The facades of the smoke saunas were clad with Finnish shou sugi ban boards, in which the surface of the wood is charred to make it weather-resistant. The contract also included building pipelines between the buildings and extending the ground source heating system with new boreholes.
Kuusijärvi is Vantaa's most popular outdoor recreation area, and it remained open throughout the contract. So we were building in the middle of an active recreation area used every day by hikers and sauna-goers.
The area stayed open the whole time
The outdoor recreation area was not closed during the contract. The site area, access routes and material deliveries had to be separated from visitors so that both could share the same terrain safely.
Special timber needs its own schedule
The charred surface of shou sugi ban cladding cannot be patched afterwards without it showing. The elements had to be protected from transport all the way to installation, and the installation sequence had to be planned before a single board was lifted.
Ground source heating and pipelines in the same terrain
The extension of the ground source heating system and the pipelines between the buildings ran through the same narrow area. The excavation sequence determined whether the building services would be ready before the interior works of the buildings.
We divided the site into four sections, one per building, and kept open only the area where work was in progress at any given time. Visitors always had a clear, fenced route to the shore and the car park.
The ground source heat boreholes were drilled and the pipelines between the buildings excavated right at the start, before the foundations took up the space. This meant the building services were ready and waiting when the frames went up.
The log structures and cladding panels were ordered to size and stored under cover on site. The facades were completed one building at a time so that the charred surface was not damaged by other site traffic.
The contract was handed over in June 2025. The area remained in use throughout construction.